Redundant SCADA & controls, off-grid operation via BESS, energy arbitrage, automatic DG start/stop, SOC management and solar firming.

Liberty Textile, Pakistan
Liberty Textile, Pakistan
ClientLiberty Textile
LocationPakistan
SectorTextile
Capacity9 MW DC Solar · 9 MW Wind
9MW solar (DC)
9MW wind
8MWh battery storage

How the site is controlled

PES SCADA and plant controlsSolar PV9 MW DCWind9 MWBattery8 MWhGridUtilityGenerators24 MW captive plant

Single-line view of what PES controls on this site: Hybrid: Wind + Solar + BESS.

Scope of work

  • Redundant SCADA & Control System to manage the complete renewables & synch with Grid & Genset + Complete Supply of weather station
  • Off-Grid Mode of complete captive plant through BESS
  • Arbitraging through renewable powers
  • Automatic Start/Stop of DGs upon failure of Grid
  • SOC management
  • Solar Firming

Project details

Client
Liberty Textile
Sector
Textile
Location
Pakistan
Project Type
Hybrid: Wind + Solar + BESS
Capacity
9 MW DC Solar · 9 MW Wind
Grid / Captive Plant
24 MW captive plant (Grid, HFOs, Gas Gensets)
Energy Storage
8 MWh BESS · 8 MW PCS (Huawei)
Key Equipment
32× Huawei 250 kW string inverters · 2× 4.5 MW WTGs