Emerge Masdar project

Redundant SCADA & controls, weather station, off-grid operation via BESS, energy arbitrage, automatic DG start/stop, SOC management and solar firming.

Emerge Masdar, Masdar, UAE
Emerge Masdar, Masdar, UAE
ClientEmerge (Masdar)
LocationMasdar, UAE
SectorCommercial & Industrial Energy
Capacity6 MW DC / 5.4 MW AC Solar
6MW solar (DC)
6MWh battery storage

How the site is controlled

PES SCADA and plant controlsSolar PV6 MW DCBattery6 MWhGeneratorsGensets

Single-line view of what PES controls on this site: Solar + BESS (Diesel Hybrid).

Scope of work

  • Redundant SCADA & Control System to manage the complete renewables & synch with Grid & Genset + Complete Supply of weather station
  • Off-Grid Mode of complete captive plant through BESS
  • Arbitraging through renewable powers
  • Automatic Start/Stop of DGs upon failure of Grid
  • SOC management
  • Solar Firming

Project details

Client
Emerge (Masdar)
Sector
Commercial & Industrial Energy
Location
Masdar, UAE
Project Type
Solar + BESS (Diesel Hybrid)
Capacity
6 MW DC / 5.4 MW AC Solar
Grid / Captive Plant
2× DGs per site
Energy Storage
6 MWh BESS · 6 MW PCS
Key Equipment
12× Sungrow 350 kW inverters